Fermentation Tank
A small dairy line is not a list of machines. It is a sequence with a rhythm, and the rhythm is set by whichever stage cannot be sped up. Most planning mistakes come from sizing one stage well and the rest by assumption.
This guide walks the sequence for a plant producing drinking milk, set yogurt and a simple fresh cheese, at a daily volume in the low hundreds of litres. The same logic holds at larger volumes; only the numbers change.
Start from the packing shift, not the tank
The packing shift is the fixed point. If the filler runs for four hours and fills 1,200 cups an hour, the plant needs 4,800 cups of product that day. Everything upstream exists to deliver that volume at the right temperature, at the right time, without a second shift.
Working forward from there:
- Product volume for packing, plus the line losses in the filler and the pipework.
- Fermentation or holding volume, which must cover the packing run without a second batch.
- Batch size in the pasteuriser, which must fill the fermentation tank within its working range.
- Reception and cooling capacity, which must handle the morning milk intake before the first batch starts.
When the four numbers line up, the line works. When they do not, one stage waits for another all day and the output is set by the slowest step.
Reception and cooling
Raw milk arrives warm and starts changing immediately. The reception stage filters it and brings it down to storage temperature quickly, usually through a plate cooler fed by chilled water or an ice bank.
Two details are worth settling early. First, the cooling load: the cooler has to remove heat at the rate the milk arrives, not at the average rate over the day. Second, the storage volume: a tank that holds one morning collection avoids a second intake run, but only if the pasteuriser can empty it before the next one.
Standardisation and homogenising
Fat standardisation adjusts the ratio of cream to skimmed milk before processing. A separator or a cream supply plus a mixing point is enough for small volumes; the arithmetic is a mass balance, and it is worth doing once with real fat figures rather than assuming a fixed recipe.
Homogenising follows, typically at 60 to 70 °C, before or after pasteurising depending on the product. It reduces fat globule size and keeps the product from separating in the pack. The pressure that matters is the pressure at the valve during the run, not the maximum the machine can reach.
Pasteurising: batch or continuous
Batch pasteurising suits a plant running several products in a day, with small volumes and frequent changeovers. The vessel heats, holds and cools the whole batch, and the cycle time includes all three steps.
Continuous pasteurising suits a single product running for hours. It heats and cools through heat exchangers and holds the product in a tube for a defined time. It is faster and more consistent, and it is less forgiving of interruptions.
The choice is usually made by the product mix. Three products a day at 300 L each points to batch. One product at 3,000 L a day points to continuous.
Fermentation
For set yogurt the product is filled into cups and fermented in the pack, so the fermentation room or cabinet becomes the constraint. For stirred yogurt it ferments in the tank and is filled afterwards, which puts the constraint back on the tank and the filler.
In both cases temperature uniformity decides quality. A tank with a jacket and slow agitation can hold a band of a degree or two across the batch; a tank with poor circulation shows a gradient from the wall to the centre, and the product sets unevenly. Working volume matters here: filling a large tank halfway leaves the top of the batch warmer than the bottom.
Filling and packing
The filler sets the rhythm for the rest of the line, and its format flexibility often matters more than its top speed. A cup filler that changes format in twenty minutes is worth more to a small dairy than one that runs faster but needs half a shift to switch.
Match the filler to the product, not the other way round:
- Thin liquids and drinking milk: piston or gravity fillers, with a clean cut-off at the nozzle.
- Viscous products and set yogurt: positive displacement or servo-driven pistons that handle texture without shearing it.
- Cups and trays: inline fill-seal machines with a film feed matched to the lane width.
Cleaning and utilities
Cleaning is a production step, not an afterthought. A line that needs four hours to strip and clean will lose half a shift, and the schedule will quietly fall behind.
Plan the cleaning route at the same time as the process route. Drain points at the low points, a spray ball in every vessel, and pipework that can be flushed without dismantling. For small plants, a single CIP unit serving the pasteuriser and the filler is usually enough.
The utilities to confirm before ordering: electrical connected load, steam or hot water capacity, chilled water temperature and flow, compressed air for valves, and floor drainage.
Common configuration mistakes
| Mistake | What it costs later |
|---|---|
| Fermentation tank larger than the batch | Poor temperature uniformity, uneven set, product wasted at low fill |
| Cooling sized on mains water in summer | Cycle time stretches, output drops in the hottest months |
| Filler bought before the pack format is fixed | Change parts cost more than the difference between two models |
| No buffer between pasteuriser and filler | Every stop upstream empties the filler, every stop downstream blocks the tank |
| Cleaning designed after layout | Dead legs and undrainable pipe, repeated hygiene problems |
What a small line looks like
For a plant packing around 4,000 cups a day, a workable sequence is: reception tank and plate cooler, 500 L batch pasteuriser, homogeniser, two 300 L fermentation tanks running on alternate days, cup fill-seal machine, and a shared CIP unit. The pasteuriser fills one fermentation tank per batch, the filler runs one shift, and the second tank ferments while the first is packed.
The numbers are illustrative, not a recommendation. What matters is that each stage is sized from the packing shift backwards, and that the buffers sit where the stops actually happen.
Where to go next
If you are planning a line, send the product, the daily volume, the pack format and the utilities you have. The first reply should be a sequence with numbers attached, not a price list.